Installing the new ski lift at Turner Ski Area
Installing the new ski lift on Turner Mountain during the summer of 2001. Photos by Steve LeFever.
(Click on pictures for larger view)

406-293-2468
www.skiturner.com
contact@skiturner.com



Click for larger image

Dismantling/Burn Crew 6/9/01


Click for larger image

Upper Concrete Transfer Station 7/21/01


Click for larger image

Setting Towers at Midway 7/21/01


Click for larger image

Pouring Tower Base at the Bottom 7/01


Click for larger image

Pouring Tower Base Near the Top 7/19/01


Click for larger image

Line Horse Setting Up at Tower 25 for an Initial Uphill Pull 10/26/01


Click for larger image

Forwarder Climbing at Old Tower 11


Click for larger image

Top Bullwheel and Towers Arriving in Parking Lot


Click for larger image

Pouring Tower Base 7/21/01


Click for larger image

Working the Brake During Line Pulling 10/29/01


Click for larger image

Line Horse set Up on Top after Cable has been pulled Around the Bullwheel 11/1/01


Click for larger image

Placing Motor Room on Bottom Terminal Rails 10/27/01


Click for larger image

Running the Tag Line Downhill 10/26/01


Click for larger image

Line Horse in Place for Final Pull 11/8/01


Click for larger image

Building the Generator Room 11/3/01


Click for larger image

Preparing to Release the Cable for Final Pull Downhill 11/8/01


Click for larger image

Generator Arrives 11/3/01


Click for larger image

Assembled Chairs Awaiting Attachment 12/2/01


Click for larger image

Temporary Ski Patrol Trailer in Place 12/2/01


Click for larger image

Chair Assemble Crew 12/2/01


Click for larger image

Bottom Terminal Painting and Construction 11/11/01


Click for larger image

Cable Detensioner, Ready to Insert the Fixed Grip 12/22/01


Click for larger image

Attaching Chair Swing Guards at Midway 12/16/01


Click for larger image

Chair Attachment Crew 12/22/01


Click for larger image

Finishing Generator Fuel Tank Containment Structure 12/16/01


Click for larger image

Sandbag Loading Crew for Chair Brake Test 12/30/01


Click for larger image

Waiting Line for First Ride. Opening Day, Saturday 1/5/02


Click for larger image

Chair Attachment Crew 12/22/01


Click for larger image

Bottom Terminal Motor Room 1/5/02


Click for larger image

Ribbon Cutting Ceremony 2/9/02


Click for larger image

Grand Opening Dedication Ceremony 2/9/02


Click for larger image

Dismantling Engine Room and Ski Patrol Room 6/2/01


Click for larger image

Time to Begin Dismantling the T-Bar 5/17/01

For more information:
Turner Mountain message phone
406-293-2468 
or visit the Turner Ski Area web site at:
www.skiturner.com

To contact Turner Ski Area by e-mail with questions and comments:
contact@skiturner.com

| HOMEAREA ATTRACTIONS | OUTDOORS | EVENTS | COMMUNITY | PHOTO GALLERY | BUSINESSES |
All page content copyright 2010. All rights reserved.
Historical pictures of Turner by Steve LeFever, used with permission.
home page
LibbyMT.com
PO Box 940, Libby, MT 59923
406-293-3608
e-mail: info@libbymt.com